Crane Operator Offshore NOGEPA 1.2 A

A crane operator moves loads on offshore installations from and to supply boats. From a great height, he must be able to communicate with his colleagues clearly. The crane operator has knowledge of the safety aspects for hoisting equipment and attaching loads. He also engages in the daily maintenance of the offshore installation. During the course Crane Operator Offshore, all of these facets are discussed.

Offshore platform

For who?
Persons assigned to operate a crane on an offshore installation.

Requirements
None.

Content
* Offshore cranes
- types and appearances
* Safety aspects hoisting equipment
- chain and chain assemblies
- steel wire rope
- slings
- special lifting equipment
- maintenance, storage and visual inspection
* attaching loads
* Communication
- hand and arm signals
* Daily maintenance
* Basic knowledge of diesel engines, hydraulics and electrical engineering.

Result
Step 1: Basic Training
The student concludes the basic training with a theoretical and practical test. If this assessment is positive, the student receives the Provisional certificate of Expertise & Registration – Crane operator offshore.

Step 2: Offshore experience
The student is running under the supervision of a certified crane operator at least 40 hours with the crane. The hours must be registered by the OIM. During the 40 hours of operation the assignments should be made ​​in the practical assignment book and be completed with satisfactory results.

Step 3: Examination (stage 3)
After this period, the student can apply for an exam at SOMA Bedrijfsopleidingen. The exam will take place at the offshore location. All practical skills are tested during the exam, including the loading and unloading of a supply boat. If the student passes the exam, he receives the authorized NOGEPA Certificate of Expertise & Registration – Crane operator offshore. This Certificate of Registration & Expertise has a fixed period of validity of 4 years.

To qualify for the refresher training the employee must make every year at least 10 hours with the crane. These hours should be registered by the OIM.

Duration
5 days.

Costs
On request

 